Replace Flooring (CES, DES, SES, SPES)

Collegeville, Davis, Salem, and Springhill Elementary Schools replace flooring surface in PE facilities.

Completed: August 2017

Estimated Costs*: $250,000 (original estimate based on replacing flooring at 3 locations: CES, DES, and SPES. SES flooring was added to job after estimate received.)

Final Costs: $312,503.14 (includes all four gyms: CES, DES, SES, and SPES)

*The estimated cost for construction were derived from square foot calculations based on several known facts such as possible site locations, timing/scheduling, extensive historical cost data on similar projects in Central Arkansas, market conditions, inflationary impact study, State POR (Program of Requirements) and years of history of working with designs of the architect selected by the district. Estimates were based on costs for 2016.